This wiki page has a list of project milestones
Phase
|
Description
|
Target
Date
|
Actual
Date
|
1
|
Project Initiation |
10th January 2011
|
10th January 2011
|
2
|
Project scope set |
12th January 2011
|
13th January 2011
|
3
|
Provisional budget set and agreed |
17th January 2011
|
15th January 2011
|
4
|
Confirm external agency to help build the new site |
28th January 2011
|
31st January 2011
|
5
|
High level concept design complete and presented to the executives |
8th February 2011
|
|
6
|
Procure production systems and software |
16th February 2011
|
|
7
|
First pass - Web site up and running. Complete internal review. |
2nd March 2011
|
|
8
|
Second pass - Web site modification incorporated from phase 7 |
9th March 2011
|
|
9
|
Beta site ready for user and load testing. |
23rd March 2011
|
|
10
|
Incorporate changes from beta testing. |
25th March 2011
|
|
11
|
NEW WEB SITE GO LIVE |
31st March 2011
|